Managing the Mess: A Housing Association's Experience with Pipe Replacement
Residents of Brf Kärraterrassen have been enduring a challenging pipe replacement project, which is a necessity given the aging infrastructure and previous leaks. The project, initiated by Riksbyggen, is set to last for eight weeks and involves not only replacing the pipe systems but also renovating all bathrooms. While the dust and construction noise are bothersome, both Riksbyggen and the housing association board have worked hard to make the process as manageable as possible for residents.
Malicka Jeremejeff, Riksbyggen's project manager, acknowledges that living without water for two months is tough. However, the potential benefits of this renovation are substantial, particularly considering the buildings are over 50 years old and have suffered from insurance damages. The urgency of the project places it in the spotlight, and Jeremejeff explains that the timing turned out to be advantageous, as the housing association received more bids than expected during procurements, despite a recession.
The financial aspect of the renovation has also been a point of relief. Initially, there were concerns about managing costs amidst high-interest rates, but through competitive bidding, Riksbyggen was able to secure construction costs significantly lower than anticipated. This efficiency allowed the association to save millions, providing a more optimistic outlook for the project's financial implications.
Residents, particularly those living on the first floor where renovations have started, have expressed both frustration and appreciation. Annelie Hillén, a board member, highlighted that fetching water from temporary sinks became an inconvenience but noted that the skilled craftsmen engaged in the work were responsive and attentive. As the days progressed, worries began to dissipate as residents found support and satisfaction in their interactions with the workers.
Riksbyggen has efficiently handled communication throughout the renovation, directly liaising with residents and ensuring that those with special needs had accommodations. For the displaced elderly residents of the housing association, Riksbyggen arranged short-term housing options, demonstrating their commitment to prioritizing resident needs through the chaos of construction.
While the project started with some chaotic communication, both Anita Trogrlic, the housing association’s chairperson, and board member Christer Johansson noted that they have seen significant improvements as the project moves forward. They credited Riksbyggen for their extensive expertise, stressing the importance of professional management in navigating such a complex endeavor.
Despite the eventual increase in housing fees associated with the project, both Trogrlic and Johansson are optimistic about the long-term benefits of the renovations. They believe that the substantial improvement in home value will outweigh any temporary inconveniences. By the end of the year, as the project reaches completion, the residents of Brf Kärraterrassen hope that their homes will be well-prepared for a sustainable future.
Riksbyggen’s role in this process underscores their commitment not only to property management but also to the creation of thriving communities. They manage a significant portfolio across Sweden, known for providing attractive and sustainable living options. As the pipe replacement continues, the residents of Brf Kärraterrassen remain hopeful for a more comfortable living environment once the dust settles.